Hey everyone! I have a problem with cure scheduling.
Basically the projectors are no longer turning off.
We have a semi-permanent install consisting of 5 projectors running diffrent content.
All IPs are set-up, and correct. They are also working all fine.
It runs for 6 days a week with a full system reboot on the the ‘off day’.
4 days we have the projectors come on at 3pm, 2 days at 2pm, each day turning off at 10pm.
However it seems that the projectors are no longer turning off and running 24/7. There were no issues for the first 3 months.
Any clues on what to do?